Treatment, Supply, and Storage Facilities Project Overview

Water Treatment Facility
(WTF)

This Groundwater Treatment Plant will initially produce 2 million gallons per day (mgd) of finished water with the ability to expand to provide 6 mgd.

The primary components will include aerators, retention basins, intermediate pumps, pressure filters, cartridge filters, high pressure pumps, nanofiltration membrane skid, degasifier,clearwell, and finished water.

Click here for pictures.

Collector Well
(CW)

The Collector Well will supply approximately 2 mgd of raw water to the Water Treatment Plant and will have a future expansion capability of supplyig raw water for approximately 6 mgd.

The Collector Well will consist of a number of horizontal collector laterals, vertical caisson, and pump house.

Click here pictures.

Intermediate Storage Facility
(ISF)

The Intermediate Storage Facility will consist of a two compartment 500,000 gallon concrete tank and the pump station. The pump station will have a capacity of 2 mgd and will also be expandable to a capacity of 6 mgd.

Click here for pictures.



Every effort is made to keep information current. If there are any questions please contact our
office for verification. If errors are found please e-mail the Webmaster.
Copyright © 2006 - present Tate Monroe Water Assn., Inc.